Sabine Pass LNG LP (SPLNG) filed its February 2013 status report on the construction of its liquefaction and export terminal project in Cameron Parish, La. SPLNG reports that engineering is now 47.0% complete, procurement is 36.0% complete, and the overall project completion is 22.0%. SPLNG states that the overall project schedule is progressing ahead of the contractual schedule basis, with Train 1 substantial completion and Train 2 substantial completion dates of February 2016 and June 2016, respectively. The report can be found on eLibrary under Docket No. CP11-72.