Eversheds Sutherland LNG Law Blog
content top

FERC to Prepare EIS for Jordan Cove LNG Project

FERC has issued a notice of its intent to prepare an environmental impact statement (EIS) for Jordan Cove Energy Project’s proposed LNG export terminal at Coos Bay, Ore. and interconnected pipeline. Comments on the scope of the EIS are due July 10, 2017....

FERC Releases Project Update for the Gulf LNG Liquefaction Project

FERC has released an update on the status of its review of Gulf LNG’s application to expand its existing LNG import terminal in Jackson County, Miss. to enable LNG exports from the terminal. FERC Staff is currently analyzing data submitted with the application and preparing a draft environmental impact statement for the project which will be released for public comment....

DOE Authorizes Non-FTA Exports from Delfin LNG Floating Terminal

The U.S. Department of Energy (DOE) has issued an order authorizing Delfin LNG, LLC (Delfin) to export domestically produced liquefied natural gas (LNG) by vessel from the proposed floating Delfin Liquefaction Facility, offshore Cameron Parish, La., to countries without a free trade agreement (non-FTA) with the United States.  The order authorizes Delfin to export LNG up to the...

DOE Releases LNG Export Data through March 2017

The U.S. Department of Energy has released its LNG Monthly data covering U.S. LNG exports from January 2017 through March 2017.  The data indicate the following cargoes of domestically produced LNG were shipped from Cheniere Energy’s Sabine Pass LNG terminal in Cameron Parish, La. during March 2017:  three to Mexico, two each to South Korea and Jordan, and one each to Pakistan, Turkey,...

Dominion Cove Point Terminal Construction 89 Percent Complete

Dominion Energy Cove Point LNG has submitted a status report to FERC covering construction at its LNG export terminal at Lusby, Md. through April 2017.  The report states that engineering and engineered equipment procurement is essentially complete, and construction is 89.0% complete.  ...

Magnolia LNG Cleared to Begin Initial Site Preparation

FERC has issued a notice granting Magnolia LNG permission to commence initial site preparation activities for the Magnolia LNG Project in Lake Charles, La.  The approval does not grant Magnolia LNG the authority to commence construction of project facilities at the LNG terminal.  ...

« Older Entries Next Entries »