Dominion Cove Point Terminal Construction 89 Percent Complete

Dominion Energy Cove Point LNG has submitted a status report to FERC covering construction at its LNG export terminal at Lusby, Md. through April 2017.  The report states that engineering and engineered equipment procurement is essentially complete, and construction is 89.0% complete.

 

 