Corpus Christi Liquefaction Files Construction Status Report

Corpus Christi Liquefaction has filed a report with FERC covering construction through July 2018 at its Corpus Christi, Texas, liquefaction and LNG export terminal. The report states that Stage 1 (Trains 1 and 2) engineering and procurement are now 100% complete; subcontract and direct hire construction work are 78.2% and 80.7% complete, respectively; and overall project completion for Stage 1 is 91.2%. Train 1 is projected to achieve substantial completion in the 1st half of 2019. Stage 2 (Train 3) engineering is 67.8% complete; procurement is 48.1% complete; subcontract and direct hire construction work are 3.9% and 3.5% complete, respectively; and overall project completion for Stage 2 is 30.1%. Train 2 is projected to achieve substantial completion in the 2nd half of 2019.