Cheniere Announces Substantial Completion of Sabine Pass Train 1

Cheniere Energy Partners, L.P. (Cheniere Partners) and Bechtel announced that they have achieved Substantial Completion of Train 1 of the Sabine Pass liquefaction and LNG export terminal project in Cameron Parish, La.  According to the press release, “commissioning has been completed and Bechtel is turning over care, custody, and control of Train 1 to Cheniere Partners.”  The first commercial deliveries for Train 1, under a sale and purchase agreement with BG Gulf Coast LNG, LLC (BG), is expected in November 2016.  Prior to that date, BG has certain rights to early cargoes produced from Train 1.

 

 

 

 