Sabine Pass LNG Files Construction Status Report

Sabine Pass LNG has filed a report with FERC on the status of construction, through September 2015, at its LNG export terminal in Sabine Pass, La. The report states that Stage 1 (Liquefaction Trains 1 and 2) overall project completion is 95.2% against the scheduled plan of 97.5%.  Fuel gas has been introduced into Train 1. Stage 2 (Liquefaction Trains 3 and 4) overall project completion is 73.6% against the scheduled plan of 79.6%.  Sabine Pass LNG noted that construction progress supports the achievement of substantial completion for Trains 1 and 2 by March 2016 and June 2016, respectively, and for Trains 3 and 4 by April 2017 and August 2017, respectively.

Back to top