Dominion Cove Point LNG Files Construction Status Report

Dominion Cove Point LNG has filed a report with FERC on construction activities through June 2015 at its LNG export terminal near Lusby, Md.  The status report states that engineering is 90% complete, procurement is 77% complete, and construction is 5.3% complete.

 