Corpus Christi Liquefaction Submits Construction Progress Report

Corpus Christi Liquefaction has filed a report with FERC covering the progress of construction of its LNG export terminal near Corpus Christi, Texas through June 2015. The report states that engineering has progressed to 66.9% compared to a plan of 65% and procurement has progressed to 20.2% completion against a plan of 12.7%.  The total Project has progressed to 15.8% complete against a planned 12.6%.  The complete FERC docket for the project can be found on eLibrary under Docket No. CP12-507.

 