Sabine Pass LNG Provides Expansion Update

Sabine Pass LNG (Sabine Pass) filed a letter with FERC updating its construction schedule of the anticipated expansion of its LNG export terminal at Cameron Parish, La. and interconnected pipeline.  Based on the substantial completion date guaranteed by Sabine Pass’ engineering, procurement and construction contractor, and assuming a June 2015 completion of the regulatory process, Sabine Pass anticipates the following:
• Begin Stage 3 Construction – June 2015
• Begin Pipeline Construction – June 2017
• Pipeline In Service – December 2018
• Train 5 In Service – December 2019
• Train 6 In Service – When commercially feasible

Back to top