Gulf LNG Liquefaction Submits Request to Initiate FERC Pre-filing Process

Gulf LNG Liquefaction (GLL) filed a request with FERC to initiate the pre-filing environmental review process for a gas liquefaction and LNG export terminal to be located at the existing Gulf LNG import terminal near Pascagoula, MS, and an interconnected pipeline.  GLL proposes to construct two LNG trains in two phases, each with a production capacity of 5 million tonnes per year.  Modifications to the existing interconnected pipeline will enable bi-directional gas flow to and from the terminal.  GLL projects in-service dates of third quarter 2019 for the Phase I facilities and third quarter 2020 for the Phase II facilities.  GLL’s request can be found here.