Sabine Pass LNG Files Monthly Construction Report

Sabine Pass LNG has submitted its monthly construction progress report for July 2013 for its LNG export terminal in Cameron Parish, La., to FERC. The report states that Stage 1 engineering is 72% complete, procurement is 65% complete, and subcontract and direct hire construction work are 25.5% and 3.3% complete, respectively. The overall project completion is 40.2%. The report states that project progress continues to support the scheduled Substantial Completion Dates for Trains 1 and 2 by February 2016 and June 2016, respectively. The report can be found here, and the complete docket for the Sabine Pass LNG export terminal can be found on eLibrary under Docket No. CP11-72.