Sabine Pass LNG Submits Monthly Construction Progress Report

Sabine Pass LNG has submitted to FERC its construction progress report for its LNG export terminal in Cameron Parish, La. for June 2013. The report states that Stage 1 engineering is 67.1% complete, procurement is 61.4% complete, and subcontract and direct hire construction work are 24.1% and 2.3% complete, respectively. The overall project completion is 37.6%. The report states that project progress continues to support the achievement of the scheduled Substantial Completion Dates for Trains 1 and 2 by February 2016 and June 2016, respectively. The report can be found here, and the complete docket for the Sabine Pass LNG export terminal can be found on eLibrary under Docket No. CP11-72.