Sabine Pass Requests FERC Authority to Install Equipment for Trains 1 and 2

Sabine Pass LNG (Sabine Pass) filed a request for FERC authority to commence installation of all equipment for Stage 1 of its LNG export project, including Train 1, Train 2, and common areas. Sabine Pass stated that it will request authority to install LNG storage tank, in-tank pumps and hazard detection and control equipment separately once the final design is complete. Sabine Pass’s request can be found here, and the complete docket for the Sabine Pass LNG export project can be found on eLibrary by searching for Docket No. CP11-72.