Sabine Pass LNG Submits Monthly Construction Progress Report

Sabine Pass LNG, L.P., filed a status report at FERC on the construction progress of its LNG export terminal in Cameron Parish, La., The report indicates that engineering was 43.0% complete and procurement was 32.1% complete as of January 2013. The overall project completion was 19.4%. Progress on the overall project was ahead of the contractual schedule. The early targets for substantial completion of Trains 1 and 2 are February, 2016, and June, 2016, respectively. Cheniere anticipates initial LNG production from Train 1 in late 2015.The report is on eLibrary under Docket No. CP11-72. 