In letter dated August 30, 2006, Crown Landing LLC urges FERC to disregard Delaware’s contention that FERC may not grant conditional authorization to site, construct, and operate an LNG terminal “until a state has acted under its CZMA and CAA delegated federal authority.” Conditions contained within FERC’s approval of the Crown Landing terminal “withhold authorization to conduct activity until CZMA and CAA requirements are met, thereby complying with the requirements of those statutes,” the company writes. Letters from Crown Landing, the State of Delaware, and DNREC may be found in the FERC e-Library in Docket No. CP04-411.