American LNG Marketing Authorized to Export to FTA Nations

The U.S. Department of Energy has issued an order authorizing American LNG Marketing LLC to export, over a 20-year term, up to 600,000 metric tons per annum (approximately 30.2 Bcf/year) of domestically produced LNG from a proposed liquefaction facility in Titusville, Fla. to nations with a Free Trade Agreement with the United States.  The LNG will be transported in approved ISO...

DOE Grants Alaska LNG Conditional Authorization to Export to Non-FTA Nations

The U.S. Department of Energy (DOE) has conditionally authorized Alaska LNG Project, LLC (Alaska LNG) to export up to approximately 20 million metric tons per annum (929 Bcf/year) of LNG produced from Alaska sources over a 30-year term.  The order permits Alaska LNG to export LNG by vessel from the proposed Alaska LNG Project in the Nikiski area of the Kenai Peninsula, Alaska to...

Eagle LNG Partners Jacksonville Files Draft Resource Reports

Eagle LNG Partners Jacksonville has filed draft Resource Reports 1 through 12 with FERC as part of the pre-filing environmental review of its proposed LNG production, storage, and export facility on the St. Johns River in Jacksonville, Fla.  As outlined in Resource Report 1’s General Project Description, LNG produced at the facility will be loaded into trucks and containers or onto...

DOE Authorizes Pieridae Energy to Export LNG to FTA Nations from Canada; Defers Non-FTA Request

The U.S. Department of Energy (DOE) issued an order granting Pieridae Energy (USA), LTD. (Pieridae) authority to export 292 Bcf/year of natural gas from the United States to Canada and, after liquefaction at Pieridae Energy (Canada) Ltd.’s proposed Goldboro LNG Project in Guysborough County, Nova Scotia, to nations with a Free Trade Agreement (FTA) with the United States.  DOE deferred...

Dominion Cove Point LNG Files Monthly Progress Report

Dominion Cove Point LNG filed a monthly status and progress report with FERC covering construction activities through April 2015 at its LNG export terminal in Lusby, Md.  The report states that engineering is 82% complete, procurement is 75% complete, and construction is 3.5% complete....

Freeport LNG Requests Initiation of Pre-Filing Procedures for Fourth Liquefaction Train

Freeport LNG Development, L.P. has filed a request with FERC for initiation of the pre-filing environmental review process for the construction of a fourth gas liquefaction train, with a production capacity of approximately 5.1 million tonnes per annum, at the Freeport LNG Liquefaction Project and LNG export terminal currently under construction on Quintana Island, Texas....