FERC Grants Port Dolphin Energy Additional Time to Construct Onshore Pipeline for Deepwater Port

FERC has approved Port Dolphin Energy LLC’s (PDE) request to extend the deadline by which PDE must complete construction to December 31, 2018 and place into service the onshore portion of a pipeline to interconnect with PDE’s proposed Deepwater Port (DWP) terminal offshore of Tampa, Fla.  The deadline is consistent with the Maritime Administration’s (MARAD) December 31, 2018 deadline for completion of the DWP with which the onshore facilities would connect.  FERC’s order can be found here, and the complete docket for the PDE pipeline can be found on eLibrary under Docket No. CP07-191.

Back to top