Sabine Pass LNG Files Construction Status Report

Sabine Pass LNG filed a report with FERC covering construction progress at its LNG export terminal in Cameron Parish, La. through May 2016.  The report states that liquefaction Train 1 substantial completion was achieved on May 27, 2016, and substantial completion for Train 2 is anticipated by late September 2016.  Trains 3 and 4 targeted substantial completion dates are April 2017 and August 2017, respectively.

 

 

 

 