Oregon LNG Submits Revisions to FERC LNG Project Application

Oregon LNG has filed a supplement to its pending FERC application to construct a bidirectional LNG terminal facility at Warrenton, Ore. and interconnected pipeline.  The supplement reflects (1) revisions to the land requirements for the LNG storage tanks and process areas, and the associated revised wetland impacts, (2) updates to the projected quarterly water needs and water sources, (3) revisions to the draft Biological Assessment and Essential Fish Habitat Assessment, and (4) pipeline route modifications.  Also included is an updated construction schedule for the project, indicating a projected in-service date for the terminal of September 2019.  The supplement can be found here, and the complete docket for the Oregon LNG project can be found on eLibrary under Docket No. CP09-6.

Back to top